20 Water Street, Canary Wharf, London

Location London
Client Aviadobio and Canary Wharf Group
Main Contractor Bulb Laboratories
Size 38,000 sq ft
Duration 19 weeks
Completion Aug 2023

Project overview

Conquest Electrical undertook the electrical design and electrical fit-out of circa 11,000 sq ft across Level 6, for the conversion of shell and core office space into an R&D facility which includes CL2 laboratories and CAT B luxury office space.

Scope of Works

The scope of works included the full electrical installation design and works comprising CAT B fit-out, including associated mains switchgear, UPS systems, underfloor power systems, general and specialist internal lighting and lighting control systems, small power, and testing and commissioning. Key deliverables included LV Distribution, Containment System, Small Power, UPS Systems, Lighting & Lighting Control, Mechanical Power, Data & Telecoms, Fire Detection & Alarm, and Testing & Commissioning.

Results

The completed works comprised the electrical design and fit-out of the R&D facility, including CL2 laboratories and CAT B office space, together with mains switchgear, UPS systems, underfloor power systems, lighting and lighting controls, small power, and testing and commissioning.

Key deliverables

  • LV Distribution
  • Containment system
  • Small power
  • UPS Systems
  • Lighting & lighting control
  • Mechanical power
  • Data & Telecoms
  • Fire Detection & Alarm
  • Testing & Commissioning